
Government
Need an Experienced Government Construction Contractor in the Southwestern United States?
Green Tanner Industrial Construction leadership has more than 15 years of experience work on government sites, including military bases, veteran hospitals, and more. Having worked within several agencies within the government ourselves, we understand how crucial it is to follow the project’s proper procedure and deliver exceptional craftsmanship with superior attention to detail. Give us a call at 480-982-0695 to get started today. We also invite you to browse our government portfolio to see examples of our government work throughout the Southwestern United States.

Government Projects
Kerrville VA Hospital, Texas
The Kerrville VA Hospital project is a mechanical upgrade of the seven floor hospital. The air handling units for the VA hospital are being replaced and reconfigured. The ceiling space on each floor is being removed and power feeds, control feeds and lighting are being replaced. Green Tanner Industrial is the electrical subcontractor on this project. Green Tanner Industrial is also subcontracted to perform the fire alarm and controls for this project.
Luke Air Force Base, Gymnasium
FY14 F-35 Squadron Operations/ Aircraft Maintenance Unit #3 Luke Air Force Base
FY16 F-35 Hangar #3 at Luke Air Force Base
The FY16 F-35 Hangar #3 is a Corp of Engineers project at Luke Air Force Base. GTI was a sub contractor for Okland Construction on this project. GTI performed all electrical aspects of this project including 15,000 Medium Voltage Construction, Lightning Protection, Cathodic Protection, Communications, Site and Building Electrical. This was a design build project. GTI provided the electrical design. GTI partners with key team members to provide its customers a complete turn key solution. For this project GTI teamed with:
Pearson Engineering
ABCOM
Simplex Grinnell
FY16 F-35 AMU and Hangar #4 at Luke Air Force Base
The FY16 F-35 AMU and Hangar #4 is a Corp of Engineers project at Luke Air Force Base. GTI was a sub contractor for Okland Construction on this project. GTI performed all electrical aspects of this project including 15,000 Medium Voltage Construction, Lightning Protection, Cathodic Protection, Communications, Site and Building Electrical. This was a design build project. GTI provided electrical design assist to AECOM. GTI partners with key team members to provide its customers a complete turn key solution. For this project GTI teamed with:
ABCOM
Simplex Grinnell
F35A Airfield Pavement at Nellis AFB in Las Vegas, NV
We are doing a new 15kV and TeleData Infrastructure to reroute of existing utilities around the first stage of a multi billion dollar expansion on the East side of Nellis AFB in Las Vegas, NV. The project includes adding seven 130ft Musco high-mast light poles and 42 5kV taxiway lighting system.
The 15kV and TeleData systems are both tying into existing pad mounted switches and existing manholes. The new reroutes are 2,300 feet each with 4 4in and 5in conduits in each ductbank as well as 7 manholes in each run. The scope of work includes pulling 15kV 250mcm cable with new termination on each end, as well as pulling all new 100pr CU and 48 str. fiber optics.
The seven 130ft Musco high-mast poles will run the borders of 2,200ft by 2,300ft.
The 42 5kV taxiway lights are tying into Nellis AFB existing system.
NRAO / VLA with Associated Universities
The Jansky Very Large Array Facility is located approximately 50 miles west of the town of Socorro in the desert of New Mexico. The facility serves as an observatory and with its 30 dishes, is able to capture information about our solar system and neighboring galaxies and relay that information to the scientific community. The VLA Electrical Infrastructure Upgrade is comprised of 3 major equipment installations. The first portion includes installation of a new 3MW CAT Generator capable of 12.47kV generation that is used throughout the site. The second portion includes installation of new Medium Voltage Siemens Switchgear which is responsible for power distribution to the site facilities. The final portion involves installation of a new switchboard in the Control Building which will service the Correlator super computer located on the second floor of the building.
FY17 F35 LAFB AMU #5
GTI Scope of Work:
Site: 12470 volt medium voltage duct bank. We will install 5000ft of concrete encased duct bank. We will install 2000ft of medium voltage cable, terminate and test cable. We will install (1) S&C PME 11 switch, (1) 750 kva medium voltage 12470 volt transformer.
We will install 20000ft of concrete ductbank 72 pair fiber and 200 pair copper communication system.
We installed (25) light poles, pole bases and electrical underground raceway.
Buildings
AMU
We installed electrical to a 29000 sf building. We achieved a LEED silver on this project. We installed LED lights throughout the building, lighting controls and convenience power.
Hanger
We installed electrical in a 17000 sf hanger. We also installed (4) F-35 270VDC converters. We also installed counter weight pits for aircraft cooling units and airplane electrical attachments.
We also will install all security and fire alarm raceway systems.
We will also design and install all communication systems.
GTI is also a UL lightning Protection contractor. We will design and install a complete lightning protection system.
FY17 F35 LAFB Communications Facility
This is temporary filler content. This content will be replaced. This is temporary filler content. This content will be replaced. This is temporary filler content. This content will be replaced. This is temporary filler content. This content will be replaced. This is temporary filler content. This content will be replaced.